Thread Rating:
  • 0 Vote(s) - 0 Average
  • 1
  • 2
  • 3
  • 4
  • 5
Test Control sheet in Hybrid Framework
#1
Not Solved
Suppose there are 5 TC_IDs with 'Y' flag. While iterating through the 1st one, there was an error which actually stops the application to get launched. You have used Recovery scenario to overcome the situation. If the application fails to launch for the 1st TC_ID, the same will happen for rest of all. How will you stop the iteration in Test Control sheet, when you know rest all are going to face the same issue?
Reply
#2
Not Solved
if you are reading the test case execution flag dynamically, then you can update the dependent/similar test cases flag to "N" - so that the similar/dependent test cases won't execute.
Thanks,
SUpputuri
Reply


Possibly Related Threads…
Thread Author Replies Views Last Post
  Does QTP/UFT support "Microsoft.Windows.Control" (one type of wpf control)? abhishikth12221 2 3,982 01-22-2014, 06:24 PM
Last Post: abhishikth12221
  Get the Parent Folder name in Test Plan for a Test from Test Lab using QTP godsown 0 6,107 09-29-2011, 04:55 PM
Last Post: godsown
  What is the difference between Global sheet and local sheet w.r.t Run on all rows venkatbatchu 7 16,181 08-12-2009, 05:33 PM
Last Post: venkatbatchu
  Generic test object root for browser / browser control HazleVillage 0 2,367 08-10-2009, 04:52 PM
Last Post: HazleVillage

Forum Jump:


Users browsing this thread: 1 Guest(s)